- Wye track to open near SE Main|20 St|21 St project
Track will allow trains to avoid backing up in Downtown Moorhead
09/07/2022 11:19 am
detail - SE Main|20 St|21 St underpass update
Three approaches to open late afternoon July 22
07/22/2022 2:40 pm
detail - SE Main|20 St|21 St Railroad Underpass Ribbon-cutting
Remarks and ribbon-cutting will start at 4 pm
07/08/2022 1:30 pm
detail - Construction Update: SE Main|20 St|21 St Underpass Project
06/06/2022 2:55 pm
detail - Construction Update: SE Main|20 St|21 St Underpass Project
04/28/2022 1:27 pm
detail - Night excavation and hauling planned for SE Main|20 St|21 St Underpass Project
Work to remove soil from temporary train tracks set for November 29-December 10
11/23/2021 2:00 pm
detail - Construction Update: SE Main|20 St|21 St Underpass Project
11/22/2021 11:38 am
detail - Construction Update: SE Main|20 St|21 St Underpass Project
10/26/2021 11:41 am
detail - Construction Update: SE Main|20 St|21 St Underpass Project
BNSF railroad bridge over SE Main Avenue under construction
09/24/2021 12:11 pm
detail - Traffic signal light at 34 St S and 4 Ave S to become permanent
Temporary signal will remain in place until replacement in 2023
08/12/2021 10:34 am
detail - Construction Update: SE Main|20 St|21 St Underpass Project
Progress Report on the SE Main Railroad Underpass
07/19/2021 3:09 pm
detail - Construction Update: SE Main|20 St|21 St Underpass Project
Head-to-Head Traffic on 21 St S in Northbound Lanes Begins Monday, October 19 and continues throughout the week.
10/16/2020 8:22 am
detail - Construction Update: SE Main|20 St|21 St Underpass Project
08/03/2020 6:47 pm
detail - Traffic Alert: 4 Ave S and 21 St S - one-way traffic
One-way traffic begins July 6 for approximately 3 weeks.
07/01/2020 4:19 pm
detail - SE Main|20 St|21 St Underpass Project Update
Slope stability corrections causing delays in project completion. Underpass opening anticipated summer 2021.
06/01/2020 8:00 am
detail - Construction Update: SE Main|20 St|21 St Underpass Project
Progress Report on the SE Main Railroad Underpass
04/29/2020 4:44 pm
detail - Construction Update: SE Main|20 St|21 St Underpass Project
The SE Main Underpass Project is approximately 63% complete. No changes are anticipated to current road closures within the next month. Construction is ongoing on retaining walls and bridges.
02/13/2020 2:33 pm
detail - Construction Update: SE Main|20 St|21 St Underpass Project
There will be no construction on the underpass project from December 22 through January 1.
12/13/2019 9:09 am
detail - Construction Update: SE Main|20 St|21 St Underpass Project
11/15/2019 8:35 am
detail - Construction Update: SE Main|20 St|21 St Underpass Project
58% of work complete, some roads are anticipated to reopen this fall, and adjustment to Oakway roundabout will be made for winter.
10/04/2019 9:29 am
detail