Below is a list of news items for the City of Moorhead with the most recent items at the top.  If you would like to see news for a certain category, you can select it from the the drop-down box labeled (All Categories).  Any news older than 90 days is automatically archived and removed from this list.

You can also subscribe to our eNotifications to automatically receive emails as we post news to the site.

Sanitary Brick Sewer Re-Lining Project Phases 2 & 3

Post Date:05/10/2023 3:58 pm

Last year, the City of Moorhead began re-lining sections of brick sewer that were nearly 100 years old. The process of re-lining the sewer pipe with a “cured-in-place pipe” (CIPP) method rather than replacing it makes it possible to do the work without major excavation of the roadway.

Phases 2 and 3 of this project begin next week: re-lining portions of pipe underneath Main Ave from 6 St to 10 St; 8 St from Main Ave to 2 Ave N; and 4 Ave N from 9 St to 11 St.

Brick Sewer 2023 General Area Map 

 

While the re-lining process eliminates major excavation, during the process sewer flows that normally travel through the brick sewer pipe need to be bypassed around the areas being lined. During this work:

  • The lining process starts with cleaning and measuring the existing sewers. During this time, lanes will be reduced where crews are working. After data is gathered, the liner will be built, which can take 4-6 weeks. This is the stage where patience is needed—there will be no visible work occurring in the neighborhood, but it is happening off-site.
  • Main Ave will occasionally be closed to through traffic, and a detour will be in place. These closures are necessary to install new manholes along the route so the liner can be inserted. The closures on Main will occur while the manholes are being installed. Main should remain open during the rest of the re-lining process, but lanes will be reduced while work crews are present.
  • 8 St will remain open as far north as Center Ave and will be closed north of Center. There will be lane reductions while crews are on site.
  • When liners are built and delivered, lane reductions will occur to allow crews to safely install the liners. After the liners have been cured, services for each property will be reopened and the entire sewer will be inspected. Lane reductions will happen during these operations as well.

More specific dates and timeframes will be communicated as the project progresses. A specific notification category (18-06-04C Brick Sewer Phase 2&3) has been set up to provide email updates on the sewer re-lining project. Please subscribe or adjust your current notification categories to stay informed throughout the project.

Media contact: Jon Atkins, Traffic Engineer, 218.299.5390