Below is a list of news items for the City of Moorhead with the most recent items at the top.  If you would like to see news for a certain category, you can select it from the the drop-down box labeled (All Categories).  Any news older than 90 days is automatically archived and removed from this list.

You can also subscribe to our eNotifications to automatically receive emails as we post news to the site.

Construction Update: SE Main|20 St|21 St Underpass Project

Post Date:06/06/2022 2:55 pm

As of June 6, 2022, the project is approximately 90 percent complete. 

  • Both the BNSF and OTVR railroad tracks are completed and operational.
  • Approximately 89% of excavation has been completed (234,000 cubic yards).
  • Approximately 95,000 feet of structural support piling installed (about 2,800 feet remaining).

Upcoming Milestones:

  • Finish storm sewer installation (early June)
  • Complete remaining piling (early June)
  • Finish retaining walls (end of June)
  • Concrete paving, curb & gutter, medians and sidewalks (early June through early July)
  • Complete underpass and open to traffic (anticipated mid-July)
  • Complete BNSF wye track and close 1 Ave S to through traffic (late July through end of August)

20/21 June 6

More >>