Below is a list of news items for the City of Moorhead with the most recent items at the top.  If you would like to see news for a certain category, you can select it from the the drop-down box labeled (All Categories).  Any news older than 90 days is automatically archived and removed from this list.

You can also subscribe to our eNotifications to automatically receive emails as we post news to the site.

Construction Update: SE Main|20 St|21 St Underpass Project

Post Date:07/19/2021 3:09 pm

The SE Main | 20 St | 21 St Underpass is approximately 80% complete.

Temporary hay bales are being removed and replaced with sound dampening curtains to help reduce noise generated by pile driving and sheet pile driving.

Underpass Project Sound Barriers 6.24.21 5

Concrete bridge decks are complete for two bridges over 21 St: one for BNSF Railway train traffic and the other for Otter Tail Valley Railroad traffic. The OTVR railroad track is completed and operational. BNSF trains will continue to use the temporary BNSF railroad track (shoo-fly) until approximately the end of October, when the permanent track is expected to be installed.

Approximately 70% of excavation has been completed (204,000 cubic yards), and 69,000 feet of structural support piling (69% of total contract amount) has been installed. The stormwater pumping station has also been completed.

A second period of night construction is expected to follow completion of the BNSF permanent track in late October/early November. More details on that will be coming in the fall.

View more information by visiting the project page at cityofmoorhead.com.

Engineering Department, 218.299.5390