Below is a list of news items for the City of Moorhead with the most recent items at the top.  If you would like to see news for a certain category, you can select it from the the drop-down box labeled (All Categories).  Any news older than 90 days is automatically archived and removed from this list.

You can also subscribe to our eNotifications to automatically receive emails as we post news to the site.

Construction Update: SE Main|20 St|21 St Underpass Project

Post Date:04/29/2020 4:44 pm

SE Main|20 St|21 St Construction Progress Report:

  • The project is approximately 66% complete.
  • Contractor is currently working on retaining walls and bridge construction.
  • Girders are to be set and decks to be poured in July on the two north bridges, weather dependent.
  • The temporary roundabout on Oak Way has been reinstalled.

Bridge Construction 04032020 

 21 St & 4 Ave  Intersection 04032020 

  

Check out additional project information. 

Engineering Department, 218.299.5390


 